City Street Information Downloads
June 2021 Street Update
Work has commenced on the 2021 street reconstruction projects. These include:
Chelmsford from Daval to Seymour
Oakview from Daval to Seymour
Water main work is substantially complete on Oakview, with storm work to commence soon. Crews will then compolete watermain work and storm water work on Chelmsford, prior to street demolition.
Improvements will include new water main; removal and replacement of the street, sidewalks, curbs; forestery; limited drainage work; lighting improvements; decorative signs.
Street work will continue through the summer months and into the fall. The contractor will use door hangers to communicate planned water disruptions and driveway access limits. Note: not all water disruptions or access issues can be planned!