September Street Update

September should be a busy month for all the street projects. Here is the scoop:
 
Ingalls should be complete, with the exception of turf restoration by Saturday, September 9th.
 
Abbey should also be complete by the 9th. Note that this project was delayed by unforeseen subgrade conditions that require some full depth reconstruction. Though this certainly caused a delay, the road will have a much longer life due to the additional work.
 
The final 'cape seal' process for those streets due for preventative maintenance will commence following the completion of INgalls street. This last component was delayed to protect the coating from construction traffic in the vicinity. Applciation should only take one or two days and will result in a finished, uniform, and black surface.
 
Sidewalk replacement is underway on Worchester. Concrete work will continue in phases throughout the reconstruction area of Worchester, Winston, and Chesterfield. Once curbing is in place, road removal and replacement can begin. While no longer ahead of schedule, the contractor still anticipates completion this season.