City Streets Updates - June 2017

Reconstruction is progressing well as we approach summer!

Forestry activities are complete.

Worchester – Water main has been installed, pressure tested, chlorinated and bacterial analysis has been completed. Service installation is expected to begin on June 13.

Chesterfield – Water main has been installed, pressure tested and chlorinated. Samples were taken on June 12.

Winston – Water main installation is underway and should be complete by June 14.

Storm Sewer - Survey was out Friday and today staking the new storm sewer on Worchester, Chesterfield. The contractor anticipates starting this work on or before June 19.

Preservation work on select downtown streets is expected to occur in late June. The disruption should be minimal.